Data Center Development: Zoning, Permitting and Litigation

Sebastian Rucci is the lead attorney and developer on a $10 billion AI data center project in California’s Imperial Valley. The project has taken him through industrial zoning, site plan review, ministerial approval, disputes over CEQA, and a federal civil rights lawsuit against the City of Imperial and several of its officials.
That experience is the core of his data center practice. He works with developers and landowners on:
- Site selection on industrial land and zoning analysis
- Site plan applications, review deadlines and “deemed approved” rules
- Ministerial approval, and disputes over whether CEQA applies
- Approvals with cities, counties and utilities
- Litigation when officials block a lawful project, including federal civil rights claims
The Imperial Valley data center case
In January 2026, Imperial Valley Computer Manufacturing, LLC filed a verified civil rights lawsuit in the United States District Court for the Southern District of California against the City of Imperial and several senior officials. The complaint alleges that the City did not act on the project’s site plans within the deadline in its own code, so the plans were deemed approved by law, and that officials retaliated after the project moved to industrial land in Imperial County.
Read the case summary, the Civil Rights Complaint (1-09-26) and the Combined Exhibits.
Court filings
Filings and court orders from the state court cases over the project. Each opens as a PDF.
Challenge to the County’s data center moratorium
Imperial Valley Computer Manufacturing, LLC v. County of Imperial, Imperial County Superior Court, Case No. ECU004800. The petition challenged the County’s data center moratorium (Ordinance No. 1616, adopted June 16, 2026) and its extension (Ordinance No. 1618, adopted July 14, 2026). The court granted the petition, found both ordinances invalid and unenforceable, and issued a peremptory writ of mandate.
- Supplemental Verified Petition for Writ of Mandate and Declaratory Relief (filed 7-15-26, 5.9 MB)
- Supplemental Brief in Support of Peremptory Writ of Mandate (filed 7-15-26)
- Petitioner’s Request for Judicial Notice (filed 7-23-26)
- Petitioner’s Supplemental Request for Judicial Notice (filed 7-27-26)
- Judgment Granting Peremptory Writ of Mandate (filed 9-04-26)
- Peremptory Writ of Mandate (issued 9-11-26)
Challenge to the data center ban initiative
DuBose, et al. v. County of Imperial, Imperial County Superior Court, Case No. ECU04709. A pre-election challenge to the Imperial County Data Center Prohibition Act initiative. After the initiative’s proponents withdrew it, the petitioners asked the court to dismiss the case as moot, and the dismissal was entered on July 1, 2026.
- Notice of Mootness and Request for Dismissal of Verified Petition as Moot (filed 5-20-26)
- Ex Parte Application for an Order Dismissing the Verified Petition as Moot (filed 6-02-26)
- Request for Dismissal (entered 7-01-26)
The City of Imperial’s CEQA case
City of Imperial v. County of Imperial, Imperial County Superior Court, Case No. ECU004457, with the Sierra Club as intervening petitioner. The case challenges County approvals for the project under the California Environmental Quality Act (CEQA). Sebastian Rucci represents the real parties in interest. The court entered final judgment on September 30, 2026, ordering the County to set aside its CEQA exemptions for the grading permit and the April 2026 lot merger; the real parties in interest are challenging the judgment.
- Final Judgment on Petition for Writ of Mandate, Writ of Administrative Mandamus, and Injunctive Relief (filed 9-30-26, 5.5 MB)
In the news
Recent coverage of the project and its court cases. Each link opens the article on the news outlet’s site.
- Newsom’s data center laws could reshape Rucci project (The Desert Review, Oct 7, 2026)
- County ends data center moratorium following court ruling (The Desert Review, Oct 6, 2026)
- Judge strikes down County freeze on data center approvals (The Desert Review, Sep 16, 2026)
- Judge poised to strike down Imperial County's data center moratorium (KPBS, Aug 28, 2026)
- Desert data center developer challenges county moratorium in court (Courthouse News Service, Jul 28, 2026)
- Judge clears way for April 7 Imperial County Board meeting on data center (The Desert Review, Apr 5, 2026)
- Court: Imperial’s CEQA Claims Are Insufficient to Challenge Data Center (Calexico Chronicle, Feb 11, 2026)
More coverage is on Sebastian Rucci in the News and on the project’s own site, imperialdatacenter.com.
Articles on the case
- By-Right Does Not Mean Backdoor: What Ministerial Approval Requires
- IVDC Court Rulings and Appeals Timeline: What Happens Next
- The Truth About Zoning: Why the IVDC Is Playing by the Rules
- Approved by Right, Blocked by Red Tape: The IVDC Permitting Fight
- Judicial Validation: The Court Confirms the IVDC’s Legal Standing
- Court Order Confirms: The IVDC Is Lawful — And the City’s Lawsuit Is Costing You